Customer
City of Corning, NY
Progress Update
Job 44814 report 6 of 6.
Customer
City of Corning, NY
Job Number
44814
Report Date
May 16, 2026
Progress Photos
22 images
Progress Update
Report 6 of 6
In this report your cab was staged, the frame was staged to continue assembly, the pump house completed initial assembly, and the body completed the paint process. In the next report your cab may begin initial assembly, the frame build may continue, the pump house may begin testing, and the body may remain staged.