City of Corning, NY report May 2, 2026

Progress Update

City of Corning, NY Report May 2, 2026

Job 44814 report 5 of 5.

Customer

City of Corning, NY

Job Number

44814

Report Date

May 2, 2026

Progress Photos

16 images

Progress Update

May 2, 2026

Report 5 of 5

In this report your cab completed the paint process, the frame was staged (no photos), the pump house was painted then staged to continue initial assembly, and the body completed fabrication. In the next report your cab may begin initial assembly, the frame may be staged, the pump house may continue initial assembly, and the body may begin the paint process.