City of Corning, NY report April 17, 2026

Progress Update

City of Corning, NY Report April 17, 2026

Job 44814 report 3 of 3.

Customer

City of Corning, NY

Job Number

44814

Report Date

April 17, 2026

Progress Photos

12 images

Progress Update

April 17, 2026

Report 3 of 3

In this report your cab was staged to begin the paint process, the frame was staged (no photos), the pump house continued initial assembly, and the body completed fabrication. In the next report your cab may begin in paint, the frame may remain staged, the pump house may be painted then staged to continue initial assembly, and the body may begin the paint process.