Customer
Bellerose Village, NY
Progress Update
Job 44794 report 7 of 11.
Customer
Bellerose Village, NY
Job Number
44794
Report Date
March 13, 2026
Progress Photos
28 images
Progress Update
Report 7 of 11
In this report your cab completed initial assembly, the frame build continued, and the pump house and the body completed initial assembly. In the next report your cab and pump house may be merged with the frame while the body may remain staged to begin initial assembly.
More Reports In This Build
Move through the full build history without returning to the overview page.
Report 11 of 11 | 12 photos
Open ReportReport 10 of 11 | 12 photos
Open ReportReport 9 of 11 | 11 photos
Open ReportReport 8 of 11 | 22 photos
Open ReportReport 7 of 11 | 28 photos
Viewing NowReport 6 of 11 | 19 photos
Open ReportReport 5 of 11 | 16 photos
Open ReportReport 4 of 11 | 9 photos
Open ReportReport 3 of 11 | 8 photos
Open ReportReport 2 of 11 | 17 photos
Open ReportReport 1 of 11 | 13 photos
Open Report