Bellerose Village, NY report February 06, 2026

Progress Update

Bellerose Village, NY Report February 06, 2026

Job 44794 report 2 of 11.

Customer

Bellerose Village, NY

Job Number

44794

Report Date

February 06, 2026

Progress Photos

17 images

Progress Update

February 06, 2026

Report 2 of 11

In this report your cab completed paint, the frame build began and was staged in Bradenton, the pump house was painted, and the body was staged. In the next report your cab may be staged to begin initial assembly, the frame build may continue, the pump house may continue initial assembly, and the body may remain staged to begin initial assembly.