Amagansett, NY report June 27, 2026

Progress Update

Amagansett, NY Report June 27, 2026

Job 41895 report 5 of 5.

Customer

Amagansett, NY

Job Number

41895

Report Date

June 27, 2026

Progress Photos

23 images

Progress Update

June 27, 2026

Report 5 of 5

In this report your cab continued through paint, the frame build continued, the pump house was painted then staged to continue assembly, and the body continued fabrication. In the next report your cab may complete the paint process, the frame build may continue, the pump house may continue initial assembly, and the body may complete the fabrication process. Due to limited staffing and the Pierce facilities 4th of July shut down next week, your next scheduled report is week ending July 11, 2026.