Customer
Amagansett, NY
Progress Update
Job 41895 report 4 of 4.
Customer
Amagansett, NY
Job Number
41895
Report Date
June 20, 2026
Progress Photos
15 images
Progress Update
Report 4 of 4
In this report your cab remained staged to continue the paint process, the frame build began, the pump house structure was fabricated, and the body began fabrication. In the next report your cab may continue through paint, the frame build may continue, the pump house structure may remain staged, and the body may continue the fabrication process.
More Reports In This Build
Move through the full build history without returning to the overview page.