Customer
City of Syracuse, NY
Progress Update
Job 40357 report 9 of 9.
Customer
City of Syracuse, NY
Job Number
40357
Report Date
May 23, 2026
Progress Photos
23 images
Progress Update
Report 9 of 9
In this report your cab and pump house were merged with the frame, the boom mount/torque box arrived and was staged, and the body began the paint process. In the next report your chassis may be staged to continue assembly, the boom mount may remain staged, and the body may continue through paint.