Greater Rochester International Airport, NY report February 13, 2026

Progress Update

Greater Rochester International Airport, NY Report February 13, 2026

Job 44599 report 4 of 8.

Customer

Greater Rochester International Airport, NY

Job Number

44599

Report Date

February 13, 2026

Progress Photos

14 images

Progress Update

February 13, 2026

Report 4 of 8

In this report your cab was staged (no photos), the pump began assembly while the pump house structure was fabricated, and the body completed fabrication and began the paint process. In the next report your cab may begin the paint process, the pump house may continue initial assembly, and the body may continue through paint.