Melville Fire Department, NY report June 27, 2026

Progress Update

Melville Fire Department, NY Report June 27, 2026

Job 44815 report 10 of 10.

Customer

Melville Fire Department, NY

Job Number

44815

Report Date

June 27, 2026

Progress Photos

95 images

Progress Update

June 27, 2026

Report 10 of 10

In this report your chassis and transverse compartment were staged, the torque box began initial assembly, the turntable module was painted, and the body remained staged. In the next report your chassis, transverse, and turntable module may be staged, the torque box may continue initial assembly, and the body may begin initial assembly. Due to limited staffing and the Pierce facilities 4th of July shut down next week, your next scheduled report is week ending July 11, 2026.