Customer
Eastchester FD, NY
Progress Update
Job 41607 report 5 of 5.
Customer
Eastchester FD, NY
Job Number
41607
Report Date
June 13, 2026
Progress Photos
17 images
Progress Update
Report 5 of 5
In this report your cab completed the paint process, the pump house began initial assembly, and the body was fabricated then staged. In the next report your cab may begin initial assembly, the pump house may continue initial assembly, and the body may begin the paint process.
More Reports In This Build
Move through the full build history without returning to the overview page.
Report 5 of 5 | 17 photos