City of Elmira, NY report May 16, 2026

Progress Update

City of Elmira, NY Report May 16, 2026

Job 41307 report 4 of 4.

Customer

City of Elmira, NY

Job Number

41307

Report Date

May 16, 2026

Progress Photos

15 images

Progress Update

May 16, 2026

Report 4 of 4

In this report the cab completed fabrication, the frame was staged (no photos), the pump house remained staged, and the body completed fabrication and paint. In the next report the cab may begin the paint process, the frame may remain staged, the pump house may be painted then staged to continue initial assembly, and the body may be staged to begin initial assembly.