Customer
Berlin, CT
Progress Update
Job 40325 report 5 of 5.
Customer
Berlin, CT
Job Number
40325
Report Date
June 20, 2026
Progress Photos
10 images
Progress Update
Report 5 of 5
In this report your cab was staged to continue the paint process, the pump house structure was staged, and the body began fabrication. In the next report your cab may continue through paint, the pump house structure may be staged, and the body may complete fabrication.