Avon, CT report June 6, 2026

Progress Update

Avon, CT Report June 6, 2026

Job 40323 report 4 of 4.

Customer

Avon, CT

Job Number

40323

Report Date

June 6, 2026

Progress Photos

22 images

Progress Update

June 6, 2026

Report 4 of 4

In this report your cab completed paint and began initial assembly, the frame build began, the pump house completed initial assembly, the torque box arrived and was staged, and the body completed fabrication and paint. In the next report your cab may continue initial assembly, the frame build may continue, the pump house may remain staged, the torque box may begin initial assembly, and the body may remain staged to begin initial assembly.

More Reports In This Build

Jump To Another Update

Move through the full build history without returning to the overview page.