West Albany NY Report July 11, 2026

West Albany NY Report July 11, 2026

Production Report

July 11, 2026

Job 40195

In this report your cab completed paint and began initial assembly, the frame build continued, the pump house completed initial assembly, and the body completed paint. In the next report your cab may continue initial assembly, the frame build may continue, the pump house may remain staged, and the body may begin initial assembly.