West Albany NY Report June 27, 2026

West Albany NY Report June 27, 2026

Production Report

June 27, 2026

Job 40195

In this report your cab continued the paint process, the frame build continued, the pump house continued initial assembly, and the body began the paint process. In the next report your cab may complete paint and begin initial assembly, the frame build may continue, the pump house may be painted then continue initial assembly, and the body may continue through paint. Due to limited staffing and the Pierce facilities 4th of July shut down next week, your next scheduled report is week ending July 11, 2026.