Selden NY Report September 26, 2026

Selden NY Report September 26, 2026

Production Report

September 26, 2026

Job 42345

In this report your cab completed paint and began initial assembly, the frame build began, the pump house remained staged to continue initial assembly, and the body began the paint process with metal finishing. In the next report your cab may continue initial assembly, the frame build may continue, the pump house may continue initial assembly, and the body may continue through paint.