New Castle FD1 NY Report July 25, 2026

New Castle FD1 NY Report July 25, 2026

Production Report

July 25, 2026

Job 45468

In this report the cab completed fabrication, the frame build began, the pump house continued initial assembly, and the body continued the fabrication process. In the next report the cab, frame and pump house may remain staged while the body may complete the fabrication process.