Liverpool NY Report August 15, 2026

Liverpool NY Report August 15, 2026

Production Report

August 15, 2026

Job 42030

In this report your cab continued the paint process, the pump house structure was fabricated and began the paint process, and the body began fabrication. In the next report your cab may continue through paint, the pump house structure may be painted then begin initial assembly, and the body may complete the fabrication process.