Berlin CT Report June 27, 2026

Berlin CT Report June 27, 2026

Production Report

June 27, 2026

Job 40325

In this report your cab continued through paint, the frame build began, the pump house began initial assembly, and the body completed fabrication. In the next report your cab may continue the paint process, the frame build may continue, the pump house may be painted then continue initial assembly, and the body may begin the paint process. Due to limited staffing and the Pierce facilities 4th of July shut down next week, your next scheduled report is week ending July 11, 2026.